Tuesday, September 18, 2007
Moving Forward in sustainabilty
Dennis has begun his process of setting the first two courses, figuring window openings and is prepared to glue/foam the block down, place re bar and start moving upward. We worked on a couple patio slabs that needed compaction and should be ready to pour when the walls are complete. The job and the job site in general is a clean great place to work with all of this great weather. The sun is on us from about 10am-3pm. Retaining walls are complete we are simply waiting on some finer points that Joel is still trying to work through to really make this project a super success. Once again you are encouraged to stop in and see how we are pushing the building envelope in residential construction. We truly are building for a sustainable Vermont.
Friday, September 14, 2007
The AMDECK is Poured
With the help of local concrete guru K. Streeter the AMDECK slab pour went well and we are ready to start setting the second floor on Monday. Joel pointed out something prior to the pour. With the radiant in the slab and working close with the plumbers the plumbing on the project is more then 50% complete, using AMDECK. The electrical will go quickly, working with local solar expert R. Rivers and his crew at suntied electric. We are planning that the whole project should be dried in by the end of September if not sooner. The invitation to stop by is still open and we had a large group of Norwich University Architectural students visit with professor T. Latham. Thanks for coming by tomorrows visionaries and give us a call with any questions. We are moving forward and hope to keep spreading the news about our AMVIC ICF project.
Monday, September 10, 2007
On the road and ready to pour
After a long day on Vermont's beautiful roads I did not have to much time to check out how much the project had moved forward though I am quite sure that the radiant is done and that Craig, aka Mr Re Bar, set what he could of the mat of steel and we could pour whenever. We are having some visitors to the job site on Wednesday and I encourage anyone interested to stop in and see us.
Friday, September 7, 2007
Ready Set Pour...Almost
The pour is coming so soon you can almost taste the chloride. The AM-Deck has been set and is waiting for a few plumbers and a solid mat of rebar, 12 or 16 o.c depending on the specs for the span. Either way we are thinking that early next week we should be starting with the second floor and setting staging by the end of the week. Meanwhile the Soprema Waterproofing has been applied and we have been back filling with the help of Jermane.
Wednesday, September 5, 2007
The AMDECK is Set
Though not completely ready for the pour the majority of the work is finished, aka all the steel joists and blocks are set. We had quite a few cuts to make since the dimensions were not exact to the AMDECK. Everyone agrees it goes up fast now we all need to prepare for the pour, set re bar construct a pour stop and brace, which should take a day. The slab will be 4 inches thick radiant will be installed prior to the pour and the floor will span the 28 feet unsupported after the pour. During the pour we will brace from below about every 14 feet in this case. For more info, CAD details, Specs and general info contact us or AMVIC. I will keep you posted.
Thursday, August 30, 2007
The walls are poured enjoy the Video!
The pour went super smooth and everyone was pleased. No issues due to a little more time taken getting ready always relieves stress. The AMDECK will start going up tomorrow before the long Labor Day weekend. Larry the plumber has done some research and he is ready for the solar installation when it is time. It wont be long now we will be drying this project in. It is so rewarding to use ICF concrete because the steps of construction are reduced and the project seems so much more complete once the walls have been poured. The studding and the R-30 walls of insulation are all included with the AMVIC Building System!
Labels:
AMVIC,
Concrete Home,
Green Building,
ICF,
VERMONT
Tuesday, August 28, 2007
Ready to pour the walls
We are braced and ready to go! Once the walls are poured the AMDECK will go up and we will move on. I will be posting some videos of the pour. Everyone is invited to come out and watch the pour ask questions and enjoy the day in Waterbury. We are pushing the building envelope to the next level, come and join us as we move forward to a better tomorrow!