The AMDECK is Poured




With the help of local concrete guru K. Streeter the AMDECK slab pour went well and we are ready to start setting the second floor on Monday. Joel pointed out something prior to the pour. With the radiant in the slab and working close with the plumbers the plumbing on the project is more then 50% complete, using AMDECK. The electrical will go quickly, working with local solar expert R. Rivers and his crew at suntied electric. We are planning that the whole project should be dried in by the end of September if not sooner. The invitation to stop by is still open and we had a large group of Norwich University Architectural students visit with professor T. Latham. Thanks for coming by tomorrows visionaries and give us a call with any questions. We are moving forward and hope to keep spreading the news about our AMVIC ICF project.