Though not completely ready for the pour the majority of the work is finished, aka all the steel joists and blocks are set. We had quite a few cuts to make since the dimensions were not exact to the AMDECK. Everyone agrees it goes up fast now we all need to prepare for the pour, set re bar construct a pour stop and brace, which should take a day. The slab will be 4 inches thick radiant will be installed prior to the pour and the floor will span the 28 feet unsupported after the pour. During the pour we will brace from below about every 14 feet in this case. For more info, CAD details, Specs and general info contact us or AMVIC. I will keep you posted.