We are getting set to pour the slab, the flat work portion of the project. Dennis, Joel, Craig and myself leveled, compacted, laid out the vapor barrier and 3 inches of EPS sheet foam. Larry our plumber will lay radiant tomorrow and we will assemble a mat of re bar. The concrete will be poured Thursday at the latest. I have to travel tomorrow visiting a few jobs around Vermont. One in Calais, VT is another complete ICF project being constructed be the home owner that I am sure will be an exciting project.